The project encompassed the construction of the first, second and third crushers, Silos, Mills, Flotation System, Grinder, Recycling Chamber, Filters, Warehouses, etc. Some of the most important structures to be specially considered are the silos, which are 41 m high structures with an area of 1625 m2, and the mills, which are large block structures of 5 m high and within an area of 1550 m2.
Among the challenges to be faced, the complexity of making the formwork for the mills, silos and first crusher is stressed since these structures imply the use of large volumes of concrete.